    1 == P3.10        Check the acquisition procedure ==
    2 
     1== P3.10        Sky background ==
     2 
    33- **Phase**             :       3 
    44- **Status**            :       Draft   
    5 - **Category**  :       Nighttime testing (functionality and operability) (C5)
    6 - **Recurrence**        :       once at commissioning
    7 - **Duration**  :       4 hours
     5- **Category**  :       Nighttime testing (functionality and operability) (C5) + Nighttime calibration (C6)
     6- **Recurrence**        :       once at commissioning and then on request.
     7- **Duration**  :       2 hours
    88
    99**Description**
    10 - Verify the acquisition sequence for SHARK-NIR
     10- Acquire a series of sky backgrounds from science images. A short sky background may also be useful for remaining deviant pixel removal.
    1111
    1212**Prerequisites**
    13 - Atmospheric conditions: should be able to see bright stars in the sky (preferably close to zenith?).
    1413- Authorize SHARK-NIR on the SX side.
    15 - Suitable bright enough target (including the possibility of performing AO).
     14- Atmospheric conditions: AO working conditions???
    1615
    1716**Procedure**
    18 - Start the acquisition sequence: collimating the telescope to reduce the aberrations, close the loop and produce better ASM flat, NCPA estimation using phase-diversity algorithm, close SHARK-NIR tip-tilt+NCPA loop, and check the PSF quality at SCICAM.
    19 - Save telemetry (open and closed loop of the ALPAO DM).
     17- Observe a blank field close to the science target (separation~10-20 arcsec)
     18- The same set-up as nighttime science observations, but AO is not running, and the coronagraph may be removed. A list of telescope offsets is added to reach an “empty” field and jitter.
    2019
    2120**Templates**
    22 - SHARKNIR_ci_acq (not released) - coronagraphic mode
    23 - SHARKNIR_di_acq (not released) - direct imaging mode
    24 - SHARKNIR_lss_acq (not released) - long slit spectroscopy mode
     21- SHARKNIR_cal_SkyBackground (not released)
    2522
    2623**Success criteria**
    27 - Successful acquisition sequence.
     24- 10% accuracy (dependent on measurement frequency)
    2825
    2926**Notes**
     27- Same as activity 7.6 in AD4
    3028
    3129**LBTO support**
    32 - AO support
    3330
    3431**Date performed and by whom**