Changes between Version 14 and Version 15 of docs/CommissioningPlan/P3.10


Ignore:
Timestamp:
02/26/21 12:26:11 (4 years ago)
Author:
kradhakrishnan
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • docs/CommissioningPlan/P3.10

    v14 v15  
    1818* Check the working and performance of the NCPA (already calibrated) baseline approach. Take images at SCICAM.
    1919* Check the phase diversity NCPA approach using Wollaston prism + DI-DBI (already calibrated). Take images at SCICAM.
     20* If the PSF after applying the calibrated NCPA is bad, we could close the SHARK-NIR shutter (can have the SOUL-AO running parallel) and do a quick internal NCPA measurement (either till the NCPA modal coefficients or until the new shape on ALPAO-DM) to confirm that the alignment of SHARK-NIR is still good. This would mean that the NCPA already calibrated is not good enough!
    2021* Measure the phase diversity NCPA approach using Wollaston prism + DI-DBI  and using real star (need to do on the spot, but script exists). Take images at SCICAM.
    21 * Digression: If the PSF after applying the calibrated NCPA is bad, we could close the SHARK-NIR shutter (can have the SOUL-AO running parallel) and do a quick internal NCPA measurement (either till the NCPA modal coefficients or until the new shape on ALPAO-DM). Confirm that the alignment of SHARK-NIR is still good.
    2222* Check the pupil position inserting the pupil lens.
    2323* Repeat for a different star (of different magnitudes and for a different elevation of the telescope). It is also good to do this for different seeing conditions.