Changes between Version 9 and Version 10 of docs/CommissioningPlan/P3.10


Ignore:
Timestamp:
02/04/21 22:49:24 (4 years ago)
Author:
kradhakrishnan
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • docs/CommissioningPlan/P3.10

    v9 v10  
    22•       **Phase**               :       3 
    33•       **Status**              :       Draft   
    4 •       **Category**            :       Nighttime testing (functionality and operability) (C4)
     4•       **Category**            :       Nighttime testing (functionality and operability) (C5) + Nighttime testing for performance (C7)
    55•       **Recurrence**  :       once at commissioning
    6 •       **Duration**            :       12 hours
     6•       **Duration**            :       3.5 nights
    77**Description**
    88•       Evaluate the NCPA working and performance using the baseline approach, phase-diversity approach using the Wollaston prism & dual-band imaging, and measurement of NCPA using SHARK-NIR internal calibration sources.
    99
    1010**Prerequisites**
    11 •       Atmospheric conditions: ?
     11•       Atmospheric conditions: TBD
    1212•       Authorize SHARK-NIR on the SX side.
    1313•       AO working.