     1 == P3.10       Verify the ADC rotation on sky ==
     2•       **Phase**               :       3 
     3•       **Status**              :       Draft   
     4•       **Category**            :       Nighttime testing (functionality and operability) (C4)
     5•       **Recurrence**  :       once at commissioning
     6•       **Duration**            :       40 minutes
     7**Description**
     8•       Evaluate
     9**Prerequisites**
     10•       Atmospheric conditions: photometric.
     11•       Authorize SHARK-NIR on the SX side.
     12•       Photometric stars as targets for every filter.
     13•       AO working.
     14•       Target(s) at different Zenith distances?
     15**Procedure**
     16•       Check the working of the ADC using different targets in varying zenith distances and observing using different science filters?
     17**Success criteria**
     18•       xxx
     19**Notes**
     20**LBTO support**
     21•       Support from LBTI/LBTO?
     22**Associated SHARK-NIR personnel**
     23•       JF, LM, MdP
     24**Date performed and by whom**