P3.0 Large spatial scale instrument and telescope flat field

  • Phase : 3
  • Status : Draft
  • Category : Nighttime testing (functionality and operability) (C5) + Nighttime calibration (C6)
  • Recurrence : before every night observations (valid for all observing modes). 2/day for CI (BB filter only).
  • Duration : 2 hours

Description

  • Flat field is taken during twilight

Prerequisites

  • Authorize SHARK-NIR on the SX side.
  • Atmospheric conditions: AO working conditions.
  • Bad pixel map, Background, or Dark.

Procedure

  • This calibration is performed by sky observation combined with a pointing scan to record a flat (including telescope large scale transmission variations) on the detector.
  • Single integration times for a given setup, using various flux levels with natural light with no coronagraph.

Templates

Success criteria

  • Width of flux distribution: 3.10-2

Notes

  • Same as activity 7.5 in AD4

LBTO support

  • Dome open during twilight

Date performed and by whom