== P2.9 Science detector calibrations (on the telescope)== - **Phase** : 2 - **Status** : Draft - **Category** : Daytime testing (functionality and operability) (C3) + Daytime calibration (C4) - **Recurrence** : on a regular basis as per the requirement - **Duration** : 1 day **Description** - After installing the SHARK-NIR at the LBT platform, the science detector is tested for all its read-out modes, windowing possibilities. Also, some of the calibration scripts are rechecked. **Prerequisites** - SCICAM cooled down. **Procedure** - Repeat the science calibrations below (some of these are performed when SHARK-NIR was in the LBT cleanroom or at Padova cleanroom. Check [wiki:/docs/CommissioningPlan/P1.11 P1.11]) for details. ||**Code**||**Activity**||**Location to perform this test**|| ||SDC1||[wiki:/docs/CommissioningPlan/SDC1 Instrumental background for science]||Padova / LBT cleanroom / LBT Platform|| ||SDC2||[wiki:/docs/CommissioningPlan/SDC2 Instrument flat field, detector linearity and bad pixels]||Padova / LBT cleanroom|| ||SDC3||[wiki:/docs/CommissioningPlan/SDC3 Wavelength calibration]||Padova / LBT cleanroom?|| ||SDC4||[wiki:/docs/CommissioningPlan/SDC4 Thermal background]||Padova / LBT cleanroom / LBT Platform|| ||SDC5||[wiki:/docs/CommissioningPlan/SDC5 Detector gain]||Padova / LBT cleanroom / LBT Platform?|| ||SDC6||[wiki:/docs/CommissioningPlan/SDC6 Detector persistence]||Padova / LBT cleanroom / LBT Platform?|| ||SDC7||[wiki:/docs/CommissioningPlan/SDC7 Spectral resolution]||Padova / LBT cleanroom|| ||SDC8||[wiki:/docs/CommissioningPlan/SDC8 Ghost calibration]||Padova|| **Templates** - SHARKNIR_cal_InstrumentBackground (not released) - SHARKNIR_gen_cal_InstrumentFlatField (not released) - SHARKNIR_lss_cal_Wavelength (not released) - SHARKNIR_gen_mon_ThermalBackground (not released) - SHARKNIR_di_mon_DetectorGain (not released) - SHARKNIR_ci_mon_DetectorPersistence (not released) - SHARKNIR_lss_mon_SpectraResolution (not released) - SHARKNIR_cal_mon_Ghost (not released) **Success criteria** - All calibrations are successfully tested. - All relevant information (files) are saved in the repository. **Notes** - The time dedicated to this activity has to be considered in combination with other activities. Parallelism is possible. **LBTO support** **Date performed and by whom**