| 1 | == P2.9 Verification of the mask centering algorithm and final contrast with SOUL-AO and turbulence at ASM== |
| 2 | |
| 3 | - **Phase** : 2 |
| 4 | - **Status** : Draft |
| 5 | - **Category** : Daytime testing (functionality and operability) (C3) + Daytime calibration (C4) |
| 6 | - **Recurrence** : once at commissioning |
| 7 | - **Duration** : 3 days |
| 8 | |
| 9 | **Description** |
| 10 | - Verify the efficiency of the mask-centering algorithm and the final contrast with SOUL-AO and artificial turbulence intruded at the ASM. |
| 11 | |
| 12 | **Prerequisites** |
| 13 | - RR is mounted on the SX side. |
| 14 | |
| 15 | **Procedure** |
| 16 | - TBW |
| 17 | |
| 18 | **Templates** |
| 19 | |
| 20 | **Success criteria** |
| 21 | - Final contrast produced for various seeing conditions matches the simulations. |
| 22 | |
| 23 | **Notes** |
| 24 | |
| 25 | **LBTO support** |
| 26 | - Authorize SHARK-NIR on the SX side. |
| 27 | - RR is mounted on the SX side. |
| 28 | - AO support |
| 29 | |
| 30 | **Date performed and by whom** |