wiki:docs/CommissioningPlan/P2.8

Version 24 (modified by kradhakrishnan, 2 years ago) (diff)

--

P2.8 Verification of the mask centering algorithm and final contrast with SOUL-AO and turbulence at ASM

  • Phase : 2
  • Status : Draft
  • Category : Daytime testing (functionality and operability) (C3)
  • Recurrence : once at commissioning
  • Duration : 3 days

Description

  • Verify the efficiency of the mask-centering algorithm and the final contrast with SOUL-AO and artificial turbulence introduced at the ASM.

Prerequisites

  • RR is mounted on the SX side.

Procedure

  • This test will be performed at zenith. However, in the end, we may check the performance at a different elevation just for verification (for this, we required the RR mounted on the SX side).
  • We will perform the test in 3 seeing conditions -0", 0.5", and 0.8".
  • For the shaped pupil, we can not create the same conditions as nighttime. However, a best-case scenario will be tested and compared with the results with simulations matching these conditions.
  • we have five masks to be tested. Each mask test is expected to take 3 hours of testing.

Templates

Success criteria

  • Final contrast produced for various seeing conditions matches the simulations.

Notes

LBTO support

  • Authorize SHARK-NIR on the SX side.
  • RR is mounted on the SX side.
  • AO support

Date performed and by whom