  • docs/CommissioningPlan/P2.8

    v15 v16  
    1111
    1212**Procedure**
    13 •       Repeat the science calibrations below (some of these are performed when SHARK-NIR was in the LBT cleanroom. Check [wiki:/docs/CommissioningPlan/P1.11 P1.11]) for details.
     13•       Repeat the science calibrations below (some of these are performed when SHARK-NIR was in the LBT cleanroom or at Padova cleanroom. Check [wiki:/docs/CommissioningPlan/P1.11 P1.11]) for details.
    1414
    1515||SDC1||[wiki:/docs/CommissioningPlan/SDC1 Instrumental background for science]||
     
    2424**Success criteria**
    2525•       All calibrations successfully tested.
    26 * All the read-out modes and windowing possibilities of the SCICAM are tested successfully.
    2726* All relevant information (files) are saved in the repository.
    2827**Notes**