    1616•       This may be repeated with the on-axis source from the RR with AO running to check for any extra features arriving from outside SHARK-NIR but from LBT mirrors or the deployable arm.
    1717•       Repeat the science calibrations as done in [wiki:/docs/CommissioningPlan/P1.9 P1.9]
     18* Perform the working of this monitoring activity [wiki:/docs/Commissioning/SNM1 Monitoring]
    1819
    1920**Success criteria**