docs/CommissioningPlan/P2.7
v1 v2 15 15 • You may take short- and long-exposures to get better contrast of the features if required. 16 16 • This may be repeated with the on-axis source from the RR with AO running to check for any extra features arriving from outside SHARK-NIR but from LBT mirrors or the deployable arm. 17 • Repeat the science calibrations as done in [wiki:/docs/CommissioningPlan/P1.9 P1.9] 18 17 19 **Success criteria** 18 20 • All the filter images saved. 19 21 **Notes** 22 • The time dedicated to this activity has to be considered in combination with the next activity, if needed. Parallelism is possible. 20 23 **LBTO support** 21 24 • Support from LBTI/LBTO?