Changes between Initial Version and Version 1 of docs/CommissioningPlan/P2.7


Ignore:
Timestamp:
03/05/20 12:30:45 (5 years ago)
Author:
kradhakrishnan
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • docs/CommissioningPlan/P2.7

    v1 v1  
     1 == P2.7        Looking for filter defects/effects/features ==
     2•       **Phase**               :       2 
     3•       **Status**              :       Draft   
     4•       **Category**            :       Daytime testing (functionality and operability) (C2)
     5•       **Recurrence**  :       once at commissioning
     6•       **Duration**            :       1 hour(s)
     7**Description**
     8•       Finding the filter defects/effects/features using different lamps within the instrument.
     9•       If required, this may be repeated for on-axis source from RR for selected or all filters while the AO loop is running (daytime)
     10**Prerequisites**
     11•       If relevant, estimate and remove the NCPA using phase-diversity method.
     12•       RR mounted on SX side.
     13**Procedure**
     14•       Take the images of all the filters using different lamps within the instrument to locate/find out the filter effects/defects/features.
     15•       You may take short- and long-exposures to get better contrast of the features if required.
     16•       This may be repeated with the on-axis source from the RR with AO running to check for any extra features arriving from outside SHARK-NIR but from LBT mirrors or the deployable arm.
     17**Success criteria**
     18•       All the filter images saved.
     19**Notes**
     20**LBTO support**
     21•       Support from LBTI/LBTO?
     22**Associated SHARK-NIR personnel**
     23•       JF, LM, MdP
     24**Date performed and by whom**