P2.6 Tip-Tilt internal fast loop test with ASM turbulence
- Phase : 2
- Status : Draft
- Category : Daytime testing (functionality and operability) (C3)
- Recurrence : after instrument installation at telescope platform
- Duration : 1 day
Description
- To verify the SHARK-NIR internal fast tip-tilt loop (using CRED2 and SHARK-NIR ALPAO DM) using the ARGOS light source (only at zenith) for various seeing conditions (0.5", 0.8" [or larger, if possible]) simulated at the ASM. This test will verify if the correction of the fast tip-tilt loop is affected by the residual turbulence for star at different magnitudes.
- Before or after the previous test, we will also perform a short test (about 30 mins long) to find the center of the field while derotating.
Prerequisites
- Knowledge of Argos light source magnitude and the possibility of tuning its brightness (more info pending from LBTO, jenny?).
- For the SN team: know in advance how many minutes of data can be downloaded from CRED2 or the ring-buffer size. Confirm 10 mins are ok.
Procedure for the Tip-Tilt internal fast loop test
- Use ARGOS light source (to be used only at zenith) and direct light towards SHARK-NIR.
- Close the SOUL AO loop to have the best ASM shape. Keep the ASM static with the best shape.
Test A1.
- Close the SHARK-NIR internal tip-tilt loop.
- Take 10mins of data at the CRED2 (at loop frame rate) and SCICAM at 500 Hz.
- Introduce 0.5" seeing at the ASM and close the loop at 500 hz.
- Close the SHARK-NIR internal tip-tilt loop.
Test A2. Repeat test A1 with 1000Hz.
Test B1.
- Take 10mins of data at the CRED2 and SCICAM.
- Introduce 0.8" seeing at the ASM and close the loop.
- Close the SHARK-NIR internal tip-tilt loop.
- Take 10mins of data at the CRED2 and SCICAM.
Test B2. Repeat test A1 with 1000Hz.
Test C.
- Repeat the above steps of test B for the differnet selected brightness of the Argos light source (TBC which magnitudes, noting that max brightness should be mag 9th in R band)
Procedure for finding the field center
- Use ARGOS light source (to be used only at zenith) and direct light towards SHARK-NIR.
- Close the SOUL AO loop to have the best ASM shape. Keep the ASM static with the best shape.
- Keep the SHARK-NIR internal tip-tilt loop OPEN.
- Move the derotator in 10 degrees (TBD) step and take an image at each position. From the data taken, estimate the center of the field.
Templates
Success criteria
- SHARK-NIR fast tip-tilt loop works efficiently within the requirements in all the seeing conditions.
- The center of field estimated.
LBTO support
- Authorize SHARK-NIR
- Permission to use SX-ASM and LBTI-AO
- SOUL-LBTI AO support
- AO support
Date performed and by whom November 10th Luca, Daniele, Elena and remote support by Fulvio