    1 == P2.6 Tip-Tilt internal fast loop test with ASM turbulence ==
     1== [[span(style=color: green, **P2.6 Tip-Tilt internal fast loop test with ASM turbulence ** )]]==
    22
    33- **Phase**             :       2 
    4 - **Status**            :       Draft   
     4- **Status**            :       [[span(style=color: green, **COMPLETE** )]]     
    55- **Category**  :       Daytime testing (functionality and operability) (C3)
    66- **Recurrence**        :       after instrument installation at telescope platform
     
    5151
    5252**Success criteria**
    53 - SHARK-NIR fast tip-tilt loop works efficiently within the requirements in all the seeing conditions and magnitudes (comparison between open-close loop variation with different injected turbulence).
     53- SHARK-NIR fast tip-tilt loop works efficiently within the requirements in all the seeing conditions and magnitudes (comparing open-close loop variation with different injected turbulence).
    5454- The center of field estimated.
    5555
     
    6262
    6363**Date performed and by whom**
    64 November 10th Luca, Daniele, Elena and remote support by Fulvio
     64- November 10th Luca, Daniele, Elena and remote support by Fulvio