    88
    99**Description**
    10 - To verify the SHARK-NIR internal fast tip-tilt loop (using CRED1 and SHARK-NIR ALPAO DM) using the ARGOS light source (only at zenith) for various seeing conditions simulated at the ASM. This test will verify if the correction of the fast tip-tilt loop is affected by residual of the turbulence, for star different magnitudes.
     10- To verify the SHARK-NIR internal fast tip-tilt loop (using CRED1 and SHARK-NIR ALPAO DM) using the ARGOS light source (only at zenith) for various seeing conditions simulated at the ASM. This test will verify if the correction of the fast tip-tilt loop is affected by the residual turbulence for star at different magnitudes.
    1111
    1212**Prerequisites**
     
    1717- Close the SOUL AO loop to have the best ASM shape. Keep the ASM static with the best shape.
    1818- Close the SHARK-NIR internal tip-tilt loop.
    19 - Take 10mins of data at the CRED2 and SCICAM.
     19- Take 10mins of data at the CRED2 (at loop frame rate) and SCICAM.
    2020- Introduce 0.5" seeing at the ASM and close the loop.
    2121- Close the SHARK-NIR internal tip-tilt loop.