== P2.5 Instrument functional checks including TCS communication test == - **Phase** : 2 - **Status** : Draft - **Category** : Daytime testing (functionality and operability) (C3) - **Recurrence** : after instrument installation at telescope platform - **Duration** : 1 day **Description** - Instrumental functional checks are performed, including the communication between the LBT TCS and SHARK-NIR system. **Prerequisites** - All electronics and services are up and running. - Cryostat is cooled down before the run (if not kept cooled between the runs). - Science detector calibrations are performed remotely before the run. **Procedure** - Basic SHARK-NIR functional tests are performed. Images are taken using the SCICAM using SHARK-NIR internal calibration sources. - Test all the TCS functionality (sending preset, ADC trajectory, etc.) needed by SHARK-NIR, detailed in AD2. Some tests mentioned below may happen in the previous run (on a best-effort basis) or have been performed remotely before the actual run. - Check if the fits-writer receives all the right values from the LBT TCS. - Check if the derotator trajectory is received from the LBT TCS. The trajectory verification with optical feedback will be done during the nighttime commissioning. - Re-check if SOUL can access the SCICAM image from the agreed-upon folder. **Templates** **Success criteria** - All the functional checks are successfully completed. - Connection to LBT TCS is working well. All the test results are successful. - The fits-writer is receiving all the right values from LBT TCS. - SOUL can retieve the SCICAM image. **Notes** - Alfio Puglisi is the contact point for the SOUL access to SCICAM images. **LBTO support** - Authorize SHARK-NIR - Permission to use SX-ASM and LBTI-AO - Permission to send preset, receiving LBT telemetry (inc. the derotator trajectory) and details for the Fitswriter. - Support from the LBT SW team for the TCS communication tests. **Date performed and by whom**