== P2.5 Synergy with LBTI AO system test == • **Phase** : 2 • **Status** : Draft • **Category** : Daytime testing (functionality and operability) (C2) • **Recurrence** : after instrument installation at telescope platform • **Duration** : 2 hour(s) **Description** • Test the synergy with the LBTI AO system. If necessary, new interaction matrices are computed with LBTI AO for the telescope SHARK-NIR collimation model. **Prerequisites** • RR mounted and SHARK-NIR aligned to telescope. **Procedure** • a • b **Success criteria** • LBTI AO system working in tandem with the SAHRK-NIR system. • New interaction matrices are created and tested? • Look at the PSF quality with closed-loop and get a new and improved daytime telescope model for SHARK-NIR? **Notes** **LBTO support** • Mount the RR on SX • Support from LBTI? **Associated SHARK-NIR personnel** • JF, LM, MdP, MM (from AZ) **Date performed and by whom**