Changes between Version 7 and Version 8 of docs/CommissioningPlan/P2.5
- Timestamp:
- 02/04/21 21:28:32 (4 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan/P2.5
v7 v8 11 11 * SHARK-NIR active and working normally. 12 12 * Cryostat cold and SCICAM working properly. 13 * Activity [wiki:/docs/CommissioningPlan/P1.1 0 P1.10] success criteria met.13 * Activity [wiki:/docs/CommissioningPlan/P1.12 P1.12] success criteria met. 14 14 * Telescope pointed to Zenith and permission to use the Argos swing arm calibration unit. 15 15