  • docs/CommissioningPlan/P2.5

    v7 v8  
    1111* SHARK-NIR active and working normally.
    1212* Cryostat cold and SCICAM working properly.
    13 * Activity [wiki:/docs/CommissioningPlan/P1.10 P1.10] success criteria met.
     13* Activity [wiki:/docs/CommissioningPlan/P1.12 P1.12] success criteria met.
    1414* Telescope pointed to Zenith and permission to use the Argos swing arm calibration unit.