Changes between Version 1 and Version 2 of docs/CommissioningPlan/P2.4
- Timestamp:
- 01/18/21 16:42:02 (4 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan/P2.4
v1 v2 4 4 • **Category** : Daytime testing (functionality and operability) (C2) 5 5 • **Recurrence** : after instrument installation at telescope platform 6 • **Duration** : 2 hour(s)6 • **Duration** : 3 days 7 7 **Description** 8 8 • SHARK-NIR is aligned to the telescope and daytime collimation model is acquired. … … 24 24 • Support from LBTI? 25 25 **Associated SHARK-NIR personnel** 26 • JF, LM, MdP, MM (from AZ) 26 27 27 **Date performed and by whom**