== P2.3 TCS communication test == - **Phase** : 2 - **Status** : Draft - **Category** : Daytime testing (functionality and operability) (C3) - **Recurrence** : after instrument installation at telescope platform - **Duration** : 2 days **Description** - Communication with the LBT TCS is tested to verify that the interface with TCS works as expected. **Prerequisites** - All electronics and services are up and running. **Procedure** - Test all the TCS functionality (sending preset, ADC trajectory, etc.) needed by SHARK-NIR, detailed in AD2. - Check if the fits-writer is receiving all the right values from the LBT TCS. - Check if the derotator trajectory is received from the LBT TCS. The trajectory verification with optical feedback will be done during the nighttime commissioning. - Re-check if SOUL can access the SCICAM image from the agreed-upon folder. **Templates** **Success criteria** - Connection to LBT TCS is working well. All the test results are successful. - The fits-writer is receiving all the right values from LBT TCS. - SOUL can retieve the SCICAM image. **Notes** - Arcetri Team remote support is required. - LBTI-AO team support is required. - Note that although the actual work needs roughly about 2 days, a lot of it can go in parallel with other activites. So, for the estimation of the total days, only 1 day from here is considered. **LBTO support** - Authorize SHARK-NIR - Permission to use SX-ASM and LBTI-AO - Permission to send preset, receiving LBT telemetry (inc. the derotator trajectory) and details for the Fitswriter. - Support from the LBT SW team **Date performed and by whom**