== [[span(style=color: green, **P2.2 Installation of SHARK-NIR and its electronics on the LBT platform** )]] == - **Phase** : 2 - **Status** : [[span(style=color: green, **COMPLETE** )]] - **Category** : Installation of SHARK-NIR at LBT platform (C2) - **Recurrence** : once (unless deemed necessary to remove SHARK-NIR from the telescope platform) - **Duration** : 7 days (including 1 day contingency) **Description** - Aligned SHARK-NIR is prepared for the Big-Lift and installed on the LBT platform. - Installation of the electronics in the cabinets, cabling, and confirming the safety & security of the instrument and area. **Prerequisites** - SHARK-NIR is aligned and ready for the lift-off. - People required to access the electronics platform have completed the needed training - Equipment temporary connected to the rails interfering with installation removed (by LBTO personnel) **Procedure** - Look at the AD3 document for the detailed procedure. - SHARK-NIR and its parts will be ready on the high bay. These components may be moved through the hatch to the telescope or moved by elevator to the telescope - shelves: use elevators - rails: use elevators - calendered structure: use elevators - shark-nir bench+ bearing on its red handling: lift up through the hatch. - camera on a cart with wheels (with a window on the bottom): lift up through the hatch or use elevators - **Day 1** - Shelves installation. (Pag. 70-89 of Installation Plan: SHARK-NIR-INAFP-MAN-001_Issue2.1) -Temporary installation of rails to identify interferences. Need to be disinstalled at end of the day, unless LBTO advises differently. - **Day 2** - 2 Rails installation. (Pag. 90-95 of Installation Plan: SHARK-NIR-INAFP-MAN-001_Issue2.1) - Installation of calendered structure on the shelves. (Pag. 95-111). At the end of the day calendered structure shall be secured to the shelves, otherwise it shall be removed, together with installation rails and procedure repeataed the next day. - **Day 3** - Install the SHARK-NIR optic bench on the calendered structure. (Pag. 111-141) - **Day 4** - Fix the cable chain. (Pag. 142-144) - Install patch boxes. (Pag. 144-145) - Fix cable from patch-boxes to instrument. - **Day 5** - Move the calendered structure at its final position. (Pag. 145-148) - SCICAM installation with MACIE already installed. (Pag. 148-163) - Installation of electronics and cabling from patch boxes to cabinets. - Prepare the deployable arm for its handling. (Pag. 164-171) - **Day 6** - Installation of the deployable arm. (Pag. 172-177) - Complete cabling. - Check movements of bearing, deployable arm, and shutter. - Cool down Cryostat. - Check the network connections and very basic functionalities after powering on. - **Day 7** - Contingency **Templates** **Success criteria** - SHARK-NIR is successfully installed on the LBT platform. - SHARK-NIR electronics are successfully installed. - Telescope is balanced. - Connect all the cables and secure them. - Reassure all the connections, nuts, bolts, etc. - Confirm the safety and security of the instrument and the area. **Notes** - Activities on High-bay and telescope. - Note that SHARK-NIR is NOT installed as a single piece. The cryostat has to be disassembled from the bearing before the installation can start. Please look into the AD3 document for details. - Note that othe Lakeshore of the SHARK-NIR electronics is installed within the LBTI electronics cabinets, the rest of the electronics is in the cabinet shared with iLocater. - check this link (https://docs.google.com/document/d/1r0SDiy9yBEfGQjDI6hCXT9hfRDRJ4dh4nNUZ3JHClJE/edit) for some details on the alignment day to day plan. - Considering October timelines, as per LBTO information. Platform installation can start at 08:00 and takes about 40 minutes. 2 people can handle it. Platform use stops at 16:00, and dismounting takes about 30 mins. - No extra crew is needed on the telescope during weekends for the platform, as the operation can be handled by personnel already available at the telescope. **LBTO support** - Crew members' support for the preparation, lift-off, and installation of SHARK-NIR and its electronics - Crane operator (cleanroom, mountain bay, LBT platform) - Safety officer - Working platform installed in front of the Gregorian focal-station SX - Hatch door SX on the UIAP platform removed - Support for the installation of electronics in the LBTO cabinet - Liquid nitrogen fill - Vacuum pump to pump down cryostat (See activity P1.4 and P1.5 for more details) - Kindly check the installation document, AD3, for more details **Date performed and by whom** **Notes**