wiki:docs/CommissioningPlan/P2.1

Version 4 (modified by kradhakrishnan, 4 years ago) (diff)

--

P2.1 Activating the instrument, basic check, initiate cryostat cool down

  • Phase : 2
  • Status : Draft
  • Category : Daytime testing (functionality and operability) (C2)
  • Recurrence : after instrument installation at telescope platform
  • Duration : 1 day

Description

  • Activating the instrument after the installation of SHARK-NIR at the telescope platform. Also, various instrument states will be tested including the emergency shutdown switch.

Prerequisites

  • SHARK-NIR installed on the LBT telescope platform.

Procedure

  • Switch on all the cabinets, follow the instrument telemetry and see if the telemetry is logging.
  • Turn on all the hardware subsystems turned on and start all the corresponding services. Check all the logs from the services.
  • Start the cryostat is cool down.
  • Test the emergency shutdown button.
  • Testing the electronics and SW rotation of the knob controlling the cool down process (LBTO side. Maria knows more details)
  • Cool down the cryostat

Success criteria

  • Activating instrument successfully.
  • All systems turned on and the services all running without any errors.
  • Cryostat cooling started and on-track.
  • Emergency shutdown button working correctly.

Notes LBTO support

  • Communicate while checking the emergency shutdown button.
  • Testing the electronics and SW working of the knob (motor) controlling the cool down.

Associated SHARK-NIR personnel

Date performed and by whom