P2.1 Activating the instrument and testing instrument states & transitions
- Phase : 2
- Status : Draft
- Category : Daytime testing (functionality and operability) (C2)
- Recurrence : after instrument installation at telescope platform
- Duration : 1 hour(s)
Description
- Activating the instrument after the installation of SHARK-NIR at the telescope platform. Also, various instrument states will be tested including the emergency shutdown switch.
Prerequisites
- SHARK-NIR installed on the LBT telescope platform.
Procedure
- Switch on all the cabinets, follow the instrument telemetry and see if the telemetry is logging.
- Turn on all the hardware subsystems turned on and start all the corresponding services. Check all the logs from the services.
- Start the cryostat is cool down.
- Test the emergency shutdown button.
Success criteria
- Activating instrument successfully.
- All systems turned on and the services all running without any errors.
- Cryostat cooling started and on-track.
- Emergency shutdown button working correctly.
Notes LBTO support
- Communicate while checking the emergency shutdown button.
Associated SHARK-NIR personnel
- JF, LM, MdP, MM (from AZ)
Date performed and by whom