P2.1 Activating the instrument, basic check, initiate cryostat cool down
- Phase : 2
- Status : Draft
- Category : Daytime testing (functionality and operability) (C2)
- Recurrence : after instrument installation at telescope platform
- Duration : 1 day
Description
- Activating the instrument after the installation of SHARK-NIR at the telescope platform. Also, the shutdown procedure will be checked.
Prerequisites
- SHARK-NIR installed on the LBT telescope platform.
Procedure
- Switch on all the cabinets, follow the instrument telemetry and see if the telemetry is logging.
- Turn on all the hardware subsystems turned on and start all the corresponding services. Check all the logs from the services.
- Check the shutdown procedure (except the cryostat warm-up).
- Testing the electronics and SW rotation of the knob controlling the cool down process (LBTI side.)
- Cool down the cryostat
Success criteria
- Activating instrument successfully.
- All systems turned on and the services all running without any errors.
- The shutdown procedure is checked and working as it should be.
- Cryostat cooling started and on-track.
Notes
LBTO support
- Testing the electronics and SW working of the knob (motor) controlling the cooldown.
- Liquid Nitrogen fill
- Vacuum pump
Associated SHARK-NIR personnel
Date performed and by whom
Comments