    1 == P2.1 Cable chain cabling and pre-lift verification==
    2 
     1== [[span(style=color: green, **P2.1 Cable chain cabling and pre-lift verification** )]]  ==
    32- **Phase**             :       2 
    4 - **Status**            :       Draft   
     3- **Status**            :       [[span(style=color: green, **COMPLETE** )]] 
    54- **Category**  :       Unpack, Assemble, and Verification     
    65- **Recurrence**        :       once (unless deemed necessary to remove SHARK-NIR from the telescope platform)
     
    87
    98**Description**
    10 - Insert due SHARK-NIR cables into the cable chain and secure them so that during bearing rotation, the cables do not pull too much. At the same time, they should adhere well to the cable chain and follow its curvature without making loops.
     9- Insert the SHARK-NIR cables into the cable chain and secure them so that the cables do not pull too much during bearing rotation. At the same time, they should adhere well to the cable chain and follow its curvature without making loops.
    1110- Verify the instrument and other components are ready for lifting to the telescope platform.
    1211