| 1 | == P2.1 Activating the instrument and testing instrument states & transitions == |
| 2 | • **Phase** : 2 |
| 3 | • **Status** : Draft |
| 4 | • **Category** : Daytime testing (functionality and operability) |
| 5 | • **Recurrence** : after instrument installation at telescope platform |
| 6 | • **Duration** : 1 hour(s) |
| 7 | **Description** |
| 8 | • Activating the instrument after the installation of SHARK-NIR at the telescope platform. Also, various instrument states will be tested including the emergency shutdown switch. |
| 9 | **Prerequisites** |
| 10 | • SHARK-NIR installed on the LBT telescope platform. |
| 11 | **Procedure** |
| 12 | • Switch on all the cabinets, follow the instrument telemetry and see if the telemetry is logging. |
| 13 | • Turn on all the hardware subsystems turned on and start all the corresponding services. Check all the logs from the services. |
| 14 | • Start the cryostat is cool down. |
| 15 | • Test the emergency shutdown button. |
| 16 | **Success criteria** |
| 17 | • Activating instrument successfully. |
| 18 | • All systems turned on and the services all running without any errors. |
| 19 | • Cryostat cooling started and on-track. |
| 20 | • Emergency shutdown button working correctly. |
| 21 | **Notes** |
| 22 | **LBTO support** |
| 23 | • Communicate while checking the emergency shutdown button. |
| 24 | **Associated SHARK-NIR personnel** |
| 25 | • JF, LM, MdP, MM (from AZ) |
| 26 | **Date performed and by whom** |