     1== P2.1 Activating the instrument and testing instrument states & transitions ==
     2•       **Phase**               :       2 
     3•       **Status**              :       Draft   
     4•       **Category**            :       Daytime testing (functionality and operability)                 
     5•       **Recurrence**  :       after instrument installation at telescope platform
     6•       **Duration**            :       1 hour(s)
     7**Description**
     8•       Activating the instrument after the installation of SHARK-NIR at the telescope platform. Also, various instrument states will be tested including the emergency shutdown switch.
     9**Prerequisites**
     10•       SHARK-NIR installed on the LBT telescope platform.
     11**Procedure**
     12•       Switch on all the cabinets, follow the instrument telemetry and see if the telemetry is logging.
     13•       Turn on all the hardware subsystems turned on and start all the corresponding services. Check all the logs from the services.
     14•       Start the cryostat is cool down.
     15•       Test the emergency shutdown button.
     16**Success criteria**
     17•       Activating instrument successfully.
     18•       All systems turned on and the services all running without any errors.
     19•       Cryostat cooling started and on-track.
     20•       Emergency shutdown button working correctly.
     21**Notes**
     22**LBTO support**
     23•       Communicate while checking the emergency shutdown button.
     24**Associated SHARK-NIR personnel**
     25•       JF, LM, MdP, MM (from AZ)
     26**Date performed and by whom**