wiki:docs/CommissioningPlan/P2.10

Version 8 (modified by kradhakrishnan, 2 years ago) (diff)

--

P2.10 Test of the templates for sky observations

  • Phase : 2
  • Status : Draft
  • Category : Daytime testing (functionality and operability) (C3)
  • Recurrence : once after instrument installation at telescope platform
  • Duration : 2 days

Description

  • To verify all the (possible) templates for sky observations, including testing the observing block template for a few specific configurations. This can test the bare flow, in the sense that we are obtaining not meaningful images, but we can test that they technically work as expected.

Prerequisites

  • Authorize SHARK-NIR on the SX side.

Procedure

  • Telescope static and pointed to the zenith for almost all the tests.
  • Only exception to zenith will be if the SHARK-NIR team could send preset to the telescope and move the telescope.

Templates

  • SHARKNIR_cal_Astrometry
  • SHARKNIR_gen_mon_DistortionMap
  • SHARKNIR_cal_Flux
  • SHARKNIR_lss_cal_AbsoluteFlux
  • SHARKNIR_lss_cal_RemoveTelluric
  • SHARKNIR_gen_cal_TelescopeFlatField
  • SHARKNIR_cal_SkyBackground
  • SHARKNIR_ci_obs
  • SHARKNIR_di_obs
  • SHARKNIR_lss_obs
  • SHARKNIR_ci_acq
  • SHARKNIR_di_acq
  • SHARKNIR_lss_acq
  • SHARKNIR_gen_tec_ActiveOptics
  • SHARKNIR_gen_tec_PointingCorrection

Success criteria

  • All the templates successfully completed.

Notes

LBTO support

  • AO support
  • If the SHARK-NIR team could can move the Telescope for these templates - SHARKNIR_ci_acq, SHARKNIR_di_acq, and SHARKNIR_lss_acq, some LBT support would be appreciated.

Date performed and by whom

  • November 22nd and 23d. Davide R., Elena, Daniele, Luca, Jacopo + Fulvio remotely connected.