== P2.0B Installation of SHARK-NIR electronics on LBT platform== - **Phase** : 2 - **Status** : Draft - **Category** : Installation of SHARK-NIR at LBT platform (C2) - **Recurrence** : once (unless deemed necessary to remove SHARK-NIR from the telescope platform) - **Duration** : 2 days. **Description** - Installation of the electronics in the cabinets, cabling, and confirming the safety & security of the instrument and area. **Prerequisites** - SHARK-NIR (main parts) are installed on the LBTO platform (activity [wiki:/docs/CommissioningPlan/P2.0A P2.0A]). **Procedure** - Look at the AD4 document for the procedure and details. **Success criteria** - SHARK-NIR electronics are successfully installed in the cabinets. - Connect all the cables and secure them. - Reassure all the connections, nuts, bolts, etc. - Confirm the safety and security of the instrument and the area. **Templates** **Notes** - Note that one (or two) rack(s) of the SHARK-NIR electronics are installed within the LBTO electronics cabinets (shared with LBTI and iLocater). - Input from Laura Funk (LBTO): Installation of the LBT platform takes around 4 hours and of course also its removal. **LBTO support** - 1-2 crew members' support for the preparation and installation of SHARK-NIR electronics. - Safety officer - Kindly check the installation document, AD3, for more details **Date performed and by whom**