== P2.0B Installation of SHARK-NIR at the LBT platform - 2== • **Phase** : 2 • **Status** : Draft • **Category** : Installation of SHARK-NIR at LBT platform (C2) • **Recurrence** : once (unless deemed necessary to remove SHARK-NIR from the telescope platform) • **Duration** : 2 days. **Description** • Installation of the electronics in the cabinets, cabling, and confirming the safety & security of the instrument and area. **Prerequisites** • SHARK-NIR (main parts) are installed on the LBTO platform (activity [wiki:/docs/CommissioningPlan/P2.0A P2.0A]). **Procedure** • Look at the AD4 document for the procedure and details. **Success criteria** • SHARK-NIR electronics successfully installed in the cabinets. • Connect all the cables and secure them. • Reassure all the connections, nuts, and bolts, etc. * Confirm the safety and security of the instrument and the area. **Notes** Note that one (or two) rack(s) of the SHARK-NIR electronics are installed within the LBTO electronics cabinets (shared with LBTI and iLocater). **LBTO support** • 1-2 crew members' support for the preparation and installation of SHARK-NIR electronics. * Safety officer * Kindly check the installation document, AD3, for more details **Associated SHARK-NIR personnel** **Date performed and by whom** **Comments**