    1 == P2.0B        Installation of SHARK-NIR at the LBT platform - 2==
    2 •       **Phase**               :       2 
    3 •       **Status**              :       Draft   
    4 •       **Category**            :       Installation of SHARK-NIR at LBT platform (C2) 
    5 •       **Recurrence**  :       once (unless deemed necessary to remove SHARK-NIR from the telescope platform)
    6 •       **Duration**            :       2 days.
     1== P2.0B        Installation of SHARK-NIR electronics on LBT platform==
     2
     3- **Phase**             :       2 
     4- **Status**            :       Draft   
     5- **Category**  :       Installation of SHARK-NIR at LBT platform (C2) 
     6- **Recurrence**        :       once (unless deemed necessary to remove SHARK-NIR from the telescope platform)
     7- **Duration**  :       2 days.
     8
    79**Description**
    8 •       Installation of the electronics in the cabinets, cabling, and confirming the safety & security of the instrument and area.
     10- Installation of the electronics in the cabinets, cabling, and confirming the safety & security of the instrument and area.
     11
    912**Prerequisites**
    10 •       SHARK-NIR (main parts) are installed on the LBTO platform (activity [wiki:/docs/CommissioningPlan/P2.0A P2.0A]).
     13- SHARK-NIR (main parts) are installed on the LBTO platform (activity [wiki:/docs/CommissioningPlan/P2.0A P2.0A]).
     14
    1115**Procedure**
    12 •       Look at the AD4 document for the procedure and details.
     16- Look at the AD4 document for the procedure and details.
     17
    1318**Success criteria**
    14 •       SHARK-NIR electronics successfully installed in the cabinets.
    15 •       Connect all the cables and secure them.
    16 •       Reassure all the connections, nuts, and bolts, etc.
    17 * Confirm the safety and security of the instrument and the area.
     19- SHARK-NIR electronics are successfully installed in the cabinets.
     20- Connect all the cables and secure them.
     21- Reassure all the connections, nuts, bolts, etc.
     22- Confirm the safety and security of the instrument and the area.
     23
     24**Templates**
     25
    1826**Notes**
    19 Note that one (or two) rack(s) of the SHARK-NIR electronics are installed within the LBTO electronics cabinets (shared with LBTI and iLocater).
     27- Note that one (or two) rack(s) of the SHARK-NIR electronics are installed within the LBTO electronics cabinets (shared with LBTI and iLocater).
    2028
    2129**LBTO support**
    22 •       1-2 crew members' support for the preparation and installation of SHARK-NIR electronics.
    23 * Safety officer
    24 * Kindly check the installation document, AD3, for more details
    25 
    26 **Associated SHARK-NIR personnel**
     30- 1-2 crew members' support for the preparation and installation of SHARK-NIR electronics.
     31- Safety officer
     32- Kindly check the installation document, AD3, for more details
    2733
    2834**Date performed and by whom**