  • docs/CommissioningPlan/P2.0B

    v3 v4  
    88•       Installation of the electronics in the cabinets, cabling, and confirming the safety & security of the instrument and area.
    99**Prerequisites**
    10 •       SHARK-NIR (main parts) are installed on the LBTO platform (P2.0A).
     10•       SHARK-NIR (main parts) are installed on the LBTO platform (activity [wiki:/docs/CommissioningPlan/P2.0A P2.0A]).
    1111**Procedure**
    1212•       Look at the AD4 document for the procedure and details.