| 1 | == P2.0B Installation of SHARK-NIR at the LBT platform - 2== |
| 2 | • **Phase** : 2 |
| 3 | • **Status** : Draft |
| 4 | • **Category** : Installation of SHARK-NIR at LBT platform (C2) |
| 5 | • **Recurrence** : once (unless deemed necessary to remove SHARK-NIR from the telescope platform) |
| 6 | • **Duration** : 2 days. |
| 7 | **Description** |
| 8 | • Installation of the electronics cabinets, cabling, and confirming the safety & security of the instrument and area. |
| 9 | **Prerequisites** |
| 10 | • SHARK-NIR (main parts) are installed on the LBTO platform (P2.0A). |
| 11 | **Procedure** |
| 12 | • Look at the AD4 document for the procedure and details. |
| 13 | **Success criteria** |
| 14 | • SHARK-NIR successfully installed at the LBT platform. |
| 15 | • Telescope is balanced. |
| 16 | • Connect all the cables and secure them. |
| 17 | • Reassure all the connections, nuts, and bolts, etc. |
| 18 | * Confirm the safety and security of the instrument and the area. |
| 19 | **Notes** |
| 20 | Note that one (or two) rack(s) of the SHARK-NIR electronics are installed within the LBTO electronics cabinets (shared with LBTI and iLocater). |
| 21 | |
| 22 | **LBTO support** |
| 23 | • Crew members' support for the preparation, lift-off, and installation of SHARK-NIR electronics cabinet |
| 24 | * Crane operator (mountain bay, LBT platform) |
| 25 | * Safety officer |
| 26 | * Working platform installed in front of the Gregorian focal-station SX, |
| 27 | * Hatch door SX on the UIAP platform removed ??? |
| 28 | * kindly check the installation document for more details |
| 29 | |
| 30 | **Associated SHARK-NIR personnel** |
| 31 | |
| 32 | **Date performed and by whom** |
| 33 | |
| 34 | **Comments** |