wiki:docs/CommissioningPlan/P2.0A

Version 6 (modified by kradhakrishnan, 3 years ago) (diff)

--

P2.0A Installation of SHARK-NIR on LBT platform

  • Phase : 2
  • Status : Draft
  • Category : Installation of SHARK-NIR at LBT platform (C2)
  • Recurrence : once (unless deemed necessary to remove SHARK-NIR from the telescope platform)
  • Duration : 2 days for preparation, 2 days for installation, and 1 day contingency.

Description

  • Aligned SHARK-NIR is prepared for the Big-Lift and installed on the LBT platform.

Prerequisites

  • SHARK-NIR is aligned and ready for the lift-off.

Procedure

  • Look at the AD3 document for the procedure and details.

Templates

Success criteria

  • SHARK-NIR is successfully installed at the LBT platform.
  • Telescope is balanced.
  • Connect all the cables and secure them.
  • Reassure all the connections, nuts, bolts, etc.

Notes

  • Note that SHARK-NIR is NOT installed as a single piece. The cryostat has to be disassembled from the bearing before the installation can start. Please look into the AD3 document for details.
  • Input from Laura Funk (LBTO): Installation of the LBT platform takes around 4 hours and of course also its removal.

LBTO support

  • Crew members' support for the preparation, lift-off, and installation of SHARK-NIR
  • Crane operator (cleanroom, mountain bay, LBT platform)
  • Safety officer
  • Working platform installed in front of the Gregorian focal-station SX
  • Hatch door SX on the UIAP platform removed
  • Support for the installation of electronics in the LBTO cabinet
  • Kindly check the installation document, AD3, for more details

Date performed and by whom