Version 2 (modified by kradhakrishnan, 4 years ago) (diff) |
---|
P2.0A Installation of SHARK-NIR at the LBT platform - 1
- Phase : 2
- Status : Draft
- Category : Installation of SHARK-NIR at LBT platform (C2)
- Recurrence : once (unless deemed necessary to remove SHARK-NIR from the telescope platform)
- Duration : 2 days for preparation, 1 day for installation , and 1 day contingency.
Description
- Aligned SHARK-NIR is prepared for the Big-Lift and installed on the LBT platform.
Prerequisites
- SHARK-NIR is aligned and ready for the lift-off.
Procedure
- Look at the AD4 document for the procedure and details.
Success criteria
- SHARK-NIR successfully installed at the LBT platform.
- Telescope is balanced.
- Connect all the cables and secure them.
- Reassure all the connections, nuts, and bolts, etc.
Notes Note that SHARK-NIR is NOT installed as a single piece. The cryostat has to be disassembled from bearing before the installation can start. Please look into the AD4 document for details.
LBTO support
- Crew members' support for the preparation, lift-off, and installation of SHARK-NIR
- Crane operator (mountain bay, LBT platform)
- Safety officer
- Working platform installed in front of the Gregorian focal-station SX,
- Hatch door SX on the UIAP platform removed
- Support for the installation of electronics in LBTI/SHARK cabinet
- kindly check the installation document for more details
Associated SHARK-NIR personnel
Date performed and by whom
Comments