== P2.0A Installation of SHARK-NIR on LBT platform== - **Phase** : 2 - **Status** : Draft - **Category** : Installation of SHARK-NIR at LBT platform (C2) - **Recurrence** : once (unless deemed necessary to remove SHARK-NIR from the telescope platform) - **Duration** : 2 days for preparation, 2 days for installation, and 1 day contingency. **Description** - Aligned SHARK-NIR is prepared for the Big-Lift and installed on the LBT platform. **Prerequisites** - SHARK-NIR is aligned and ready for the lift-off. **Procedure** - Look at the AD3 document for the procedure and details. **Templates** **Success criteria** - SHARK-NIR is successfully installed at the LBT platform. - Telescope is balanced. - Connect all the cables and secure them. - Reassure all the connections, nuts, bolts, etc. **Notes** - Note that SHARK-NIR is NOT installed as a single piece. The cryostat has to be disassembled from the bearing before the installation can start. Please look into the AD3 document for details. - Input from Laura Funk (LBTO): Installation of the LBT platform takes around 4 hours and of course also its removal. **LBTO support** - Crew members' support for the preparation, lift-off, and installation of SHARK-NIR - Crane operator (cleanroom, mountain bay, LBT platform) - Safety officer - Working platform installed in front of the Gregorian focal-station SX - Hatch door SX on the UIAP platform removed - Support for the installation of electronics in the LBTO cabinet - Kindly check the installation document, AD3, for more details **Date performed and by whom**