== P2.0 Installation of SHARK-NIR at the LBT platform - 1== • **Phase** : 2 • **Status** : Draft • **Category** : Installation of SHARK-NIR at LBT platform (C2) • **Recurrence** : once (unless deemed necessary to remove SHARK-NIR from the telescope platform) • **Duration** : 2 days for preparation, 1 day for installation , and 1 day contingency. **Description** • Aligned SHARK-NIR is prepared for the Big-Lift and installed on the LBT platform. **Prerequisites** • SHARK-NIR is aligned and ready for the lift-off. **Procedure** • Look at the AD4 document for the procedure and details. **Success criteria** • SHARK-NIR successfully installed at the LBT platform. • Telescope is balanced. • Connect all the cables and secure them. • Reassure all the connections, nuts, and bolts, etc. **Notes** Note that SHARK-NIR is NOT installed as a single piece. The cryostat has to be disassembled from bearing before the installation can start. Please look into the AD4 document for details. **LBTO support** • Crew members' support for the preparation, lift-off, and installation of SHARK-NIR * Crane operator (mountain bay, LBT platform) * Safety officer * Working platform installed in front of the Gregorian focal-station SX, * Hatch door SX on the UIAP platform removed * Support for the installation of electronics in LBTI/SHARK cabinet * kindly check the installation document for more details **Associated SHARK-NIR personnel** **Date performed and by whom** **Comments**