P1.7 Verification of the operability of the motors and light sources
- Phase : 1
- Status : Draft
- Category : Unpack, Assemble, Verification, and Installation (C1)
- Recurrence : once
- Duration : half a day
Description
- Checking the working of motors and light sources within SHARK-NIR
Prerequisites
- SHARK-NIR connected to LBT network.
- Electronics cabinets on.
- DM best shape uploaded (shape minimizing internal aberrations)
- The cryostat should be running and cooled down.
Procedure
- When the services are up and running, after the motors are homed, each of the individual motors is individually tested for their different named/nominal positions.
- The light sources within SHARK-NIR are used simultaneously to check the working of the motors looking at the optical feedback.
- Check the CRED-2 and ALPAO-DM SW and optical feedback.
Success criteria
- All the motors can reach the named positions / nominal positions.
- All the light sources are working and confirmed through optical feedback at the SCICAM.
- CRED-2 AND ALPAO-DM working normally.
Notes
LBTO support
Associated SHARK-NIR personnel
Date performed and by whom
Comments Mmmmm, not super sure what this test means. The operability of the motors has already been tested when you initialized them the first time (in the sense, you know they are moving). If with "reaching the nominal position" you mean that they reach the foreseen number of steps for each saved position, I agree this can be done now, while if optical feedback is required, this is better to be done after the internal alignment of the instrument has been checked.