    55- **Category**  :       Unpack, Assemble, and Verification (C1)
    66- **Recurrence**        :       once
    7 - **Duration**  :       1.5
     7- **Duration**  :       1.5 days
    88
    99**Description**
     
    1717
    1818**Procedure**
    19 - When the services are up and running, after the motors are homed, each of the individual motors is individually tested for their different named/nominal positions.
     19- When the services are up and running, after the motors are sent to home positions, each of the individual motors is individually tested for their different named/nominal positions.
    2020- The light sources within SHARK-NIR are used simultaneously to check the working of the motors looking at the optical feedback.
    21 - Check the CRED-2 and ALPAO-DM SW and optical feedback.
     21- Check the CRED-2 and ALPAO-DM SW using optical feedback.
    2222- Take the images of all the filters using the internal calibration source (flat-field) within the instrument to locate/find out the filter defects/artefacts, if any. You may take short- and long-exposures to get better contrast of the features if required.
    2323- Check the filter wheel position monitoring script detailed in [wiki:/docs/Commissioning/SNM1 SNM1]. Save the data in the repository.