P1.5 SW checks and motors initializations
- Phase : 1
- Status : Draft
- Category : Unpack, Assemble, and Verification (C1)
- Recurrence : once
- Duration : 1 day
Description
- When the electronics are switched on, verify individual services working and initialize the motors, send to nominal positions, and verify the logging.
Prerequisites
- SHARK-NIR connected to the LBT network (P1.4 should be completed).
- Electronics on.
- A script to initialize the motors.
Procedure
- Switch on the electronics cabinets and individual components.
- Start individual services.
- Initialize all motors together (using the buttons in the final SW GUI).
- Check also the button which puts every moving component in its resting position.
- Check in the final version of the SW GUI if the individual initialization buttons work.
- Check if the SW (HW if present and need to be checked) limit switches are triggered and check the logs.
- Check if the SW part of switching ON and OFF lamps in the calibration unit works.
- Check the electronics/SW of the CRED-2 and ALPAO-DM (& RTC). Make sure that they both can be individually switched on and off remotely.
- Start the SCICAM electronics and acquire (and store) an image in warm conditions.
Templates
Success criteria
- All the services are up and running with no fatal errors and understand the errors or warnings if any.
- All the motors are working, initialized, and sent to the nominal positions.
- CRED-2 and ALPAO-DM electronics and SW working as expected.
Notes
LBTO support
Date performed and by whom