P1.4 Cable in the instrument, power on, install workstations, and connect to LBT network

  • Phase : 1
  • Status : Draft
  • Category : Unpack, Assemble, Verification, and Installation (C1)
  • Recurrence : once
  • Duration : half a day

Description

  • At the LBT clean room, cable in the instrument. Power on the cabinets, install workstations and connect SHARK-NIR to the LBT network.

Prerequisites

  • All the necessary tools and safety features to do the cabling. A free and accessible network port to connect SHARK-NIR to the LBT network.

Procedure

  • Carefully cable in SHARK-NIR.
  • Switch on the electronics cabinets.
  • Install the instrument workstation (and its copy/backup?) and the scientific camera (SCICAM) workstation in the server room.
  • Connect SHARK-NIR to the LBT network.
  • Ready essential laptops ready with all the relevant software for the cleanroom activity. Check the connection with both the workstations mentioned earlier.

Success criteria

  • Electronics cabinets are powered on (working of led lights, fans, etc.).
  • SHARK-NIR can be accessed through the LBT network (e.g. Switching on/off services remotely from the control room).

Notes

LBTO support

  • IT Support to connect to the LBT network.
  • Any electronics support needed?

Associated SHARK-NIR personnel

Date performed and by whom

Comments