P1.4 Cable in the instrument, power on, install workstations, and connect to LBT network
- Phase : 1
- Status : Draft
- Category : Unpack, Assemble, and Verification (C1)
- Recurrence : once
- Duration : 1 day
Description
- At the LBT clean room, cable in the instrument. Power on the electronics, install workstations (in the server room) and connect SHARK-NIR to the LBT network.
Prerequisites
- Presence of all the necessary tools and safety features to do the cabling. A free and accessible network port to connect SHARK-NIR to the LBT network.
Procedure
- Carefully cable in SHARK-NIR.
- Switch on the electronics.
- Install the instrument workstation (and its copy/backup) and the scientific camera (SCICAM) workstation in the server room.
- Connect SHARK-NIR to the LBT network.
- Ready essential laptops ready with all the relevant software for the cleanroom activity. Check the connection with both the workstations mentioned earlier.
Templates
Success criteria
- Electronics is powered on (working of led lights, fans, etc.).
- SHARK-NIR can be accessed through the LBT network (e.g. Switching on/off services remotely from the control room).
Notes
- SCICAM is redundant with other SCICAM computers inside of LBTI. There will not be a separate SCICAM workstation copy/backup.
LBTO support
- Need 2 free and accessible network ports to connect (a) the SHARK-NIR instrument network switch to the LBTO network, and (b) a working laptop/computer to the LBTO network.
- We need fiber link connection from the cleanroom to the server room.
- IT support to install/set the workstations in the proper location, connect to the LBT network.
- At the server room, we need 9 free network ports to connect SHARKNIRWS, SHARKNIRWS2, SASHAWS to the LBTO network. Also, we need 6 free standard electric plugs.
- At the cleanroom, we will need 1 power plug for the surge suppressor, and the maximum expected load will be of the order of 880W. Our PDUs connected to the surge suppressor. Also, couple of other normal power plugs for connecting laptops, monitors, etc. An extension power strip, if available, will be good.
- LBTO SW support may be needed.
Date performed and by whom