Version 10 (modified by kradhakrishnan, 4 years ago) (diff) |
---|
P1.4 Cable in the instrument, power on, install workstations, and connect to LBT network
- Phase : 1
- Status : Draft
- Category : Unpack, Assemble, Verification, and Installation (C1)
- Recurrence : once
- Duration : half a day
Description
- At the LBT clean room, cable in the instrument. Power on the cabinets, install workstations and connect SHARK-NIR to the LBT network.
Prerequisites
- All the necessary tools and safety features to do the cabling. A free and accessible network port to connect SHARK-NIR to the LBT network.
Procedure
- Carefully cable in SHARK-NIR.
- Switch on the electronics cabinets.
- Install the instrument workstation (and its copy/backup?) and the scientific camera (SCICAM) workstation in the server room.
- Connect SHARK-NIR to the LBT network.
- Ready essential laptops ready with all the relevant software for the cleanroom activity. Check the connection with both the workstations mentioned earlier.
Success criteria
- Electronics cabinets are powered on (working of led lights, fans, etc.).
- SHARK-NIR can be accessed through the LBT network (e.g. Switching on/off services remotely from the control room).
Notes
LBTO support
- IT Support to connect to the LBT network.
- Any electronics support needed?
Associated SHARK-NIR personnel
Date performed and by whom
Comments
- for MM: check back up for SCICAM workstation.
Attachments (1)
- SHARK-NIR_Computer_Structure.png (101.2 KB) - added by kradhakrishnan 3 years ago.
Download all attachments as: .zip