== P1.4 Cable in the instrument, power on, install workstations, and connect to LBT network == - **Phase** : 1 - **Status** : Draft - **Category** : Unpack, Assemble, and Verification (C1) - **Recurrence** : once - **Duration** : 1 day **Description** - At the LBT clean room, cable in the instrument. Power on the electronics, install workstations (in the server room) and connect SHARK-NIR to the LBT network. **Prerequisites** - Presence of all the necessary tools and safety features to do the cabling. A free and accessible network port to connect SHARK-NIR to the LBT network. **Procedure** - Carefully cable in SHARK-NIR. - Switch on the electronics. - Install the instrument workstation (and its copy/backup) and the scientific camera (SCICAM) workstation in the server room. - Connect SHARK-NIR to the LBT network. - Ready essential laptops ready with all the relevant software for the cleanroom activity. Check the connection with both the workstations mentioned earlier. **Templates** **Success criteria** - Electronics is powered on (working of led lights, fans, etc.). - SHARK-NIR can be accessed through the LBT network (e.g. Switching on/off services remotely from the control room). **Notes** - SCICAM is redundant with other SCICAM computers inside of LBTI. There will not be a separate SCICAM workstation copy/backup. - Precautionary Warning (for INAF people): Before switching on the Mocon electronics and Lakeshore, check that they are set to 115V use. **LBTO support** - Need 2 free and accessible network ports to connect (a) the SHARK-NIR instrument network switch to the LBTO network, and (b) a working laptop/computer to the LBTO network. - We need fiber link connection from the cleanroom to the server room. - IT support to install/set the workstations in the proper location, connect to the LBT network. - At the server room, we need 9 free network ports to connect SHARKNIRWS, SHARKNIRWS2, SASHAWS to the LBTO network. Also, we need 6 free standard electric plugs. - At the cleanroom, we will need 1 power plug for the surge suppressor, and the maximum expected load will be of the order of 880W. Our PDUs will be connected to the surge suppressor. Also, a couple of other normal power plugs for connecting laptops, monitors, etc. are required along with an extension power strip. - LBTO SW support may be needed. [[Image(SHARK-NIR_Computer_Structure.png​,50%)]] **Date performed and by whom**