== P1.4 Cable in the instrument, power on, install workstations, and connect to LBT network == • **Phase** : 1 • **Status** : Draft • **Category** : Unpack, Assemble, and Verification (C1) • **Recurrence** : once • **Duration** : half a day **Description** • At the LBT clean room, cable in the instrument. Power on the cabinets, install workstations, and connect SHARK-NIR to the LBT network. **Prerequisites** • All the necessary tools and safety features to do the cabling. A free and accessible network port to connect SHARK-NIR to the LBT network. **Procedure** • Carefully cable in SHARK-NIR. • Switch on the electronics. • Install the instrument workstation (and its copy/backup) and the scientific camera (SCICAM) workstation in the server room. • Connect SHARK-NIR to the LBT network. * Ready essential laptops ready with all the relevant software for the cleanroom activity. Check the connection with both the workstations mentioned earlier. **Success criteria** • Electronics is powered on (working of led lights, fans, etc.). • SHARK-NIR can be accessed through the LBT network (e.g. Switching on/off services remotely from the control room). **Notes** **LBTO support** • IT Support to connect to the LBT network. • SW support may be needed. **Associated SHARK-NIR personnel** **Date performed and by whom** **Comments** * for MM: check back up for SCICAM workstation.