Changes between Version 33 and Version 34 of docs/CommissioningPlan/P1.4


Ignore:
Timestamp:
06/29/22 22:38:38 (2 years ago)
Author:
kradhakrishnan
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • docs/CommissioningPlan/P1.4

    v33 v34  
    5454- It was necessary to add gateway 192.168.61.1 to all our devices.
    5555- Currently we do not have a nameserver, so we have to use IP addresses. Soon, we will have something such as .shark-nir.lbto.org
    56 - Shutdown and startup scripts have been tested. Several templates have been tested. All motors are moving as expected.
    57 - We tested the functionality of the LS-180 stage (deployable arm) with Mercury and Mikromove, and all was fine. It was reinserted in Box-3, which can now be stored until the next run.
    58 - We had a couple of minor issues (one with bearing limit switches, which were adjusted, and one with one ADC motor, both solved). We defined new SW limit switches to be included for bearing derotation: [131 deg, 318.5 deg].
    59 - We installed a support flange (removing part of it because of mechanical interference) to hold a technical camera (AVT Alvium 1800 U-2040m (pixel size of 2.74 um) in place of the SCICAM and acquired an image of the PSF, which looks nice. The next step is the scientific analysis of FWHM both broadband and with a narrow (10 nm) 633nm filter.
    60 - Manny, Ken, and the SCICAM will likely come up the summit on Thursday 30th (30-06-2022) afternoon, it will be then vacuumed and cooled down.
     56
    6157
    6258