    11== P1.4 Cable in the instrument, power on, install workstations, and connect to LBT network ==
    2 •       **Phase**               :       1 
    3 •       **Status**              :       Draft   
    4 •       **Category**            :       Unpack, Assemble, and Verification (C1)
    5 •       **Recurrence**  :       once
    6 •       **Duration**            :       1 day
     2- **Phase** :   1 
     3- **Status** :  Draft   
     4- **Category** :        Unpack, Assemble, and Verification (C1)
     5- **Recurrence** :      once
     6- **Duration** :        1 day
     7
    78**Description**
    8 •       At the LBT clean room, cable in the instrument. Power on the electronics, install workstations and connect SHARK-NIR to the LBT network.
     9- At the LBT clean room, cable in the instrument. Power on the electronics, install workstations and connect SHARK-NIR to the LBT network.
     10
    911**Prerequisites**
    10 •       All the necessary tools and safety features to do the cabling. A free and accessible network port to connect SHARK-NIR to the LBT network.
     12- All the necessary tools and safety features to do the cabling. A free and accessible network port to connect SHARK-NIR to the LBT network.
     13
    1114**Procedure**
    12 •       Carefully cable in SHARK-NIR.
    13 •       Switch on the electronics.
    14 •       Install the instrument workstation (and its copy/backup) and the scientific camera (SCICAM) workstation in the server room.
    15 •       Connect SHARK-NIR to the LBT network.
    16 *  Ready essential laptops ready with all the relevant software for the cleanroom activity. Check the connection with both the workstations mentioned earlier.
     15- Carefully cable in SHARK-NIR.
     16- Switch on the electronics.
     17- Install the instrument workstation (and its copy/backup) and the scientific camera (SCICAM) workstation in the server room.
     18- Connect SHARK-NIR to the LBT network.
     19- Ready essential laptops ready with all the relevant software for the cleanroom activity. Check the connection with both the workstations mentioned earlier.
     20
     21**Templates**
     22
    1723**Success criteria**
    18 •       Electronics is powered on (working of led lights, fans, etc.).
    19 •       SHARK-NIR can be accessed through the LBT network (e.g. Switching on/off services remotely from the control room).
     24- Electronics is powered on (working of led lights, fans, etc.).
     25- SHARK-NIR can be accessed through the LBT network (e.g. Switching on/off services remotely from the control room).
     26
    2027**Notes**
    21 * SCICAM is redundant with other SCICam computers inside of LBTI. There will not be a separate SCICAM workstation copy/backup.
     28- SCICAM is redundant with other SCICam computers inside of LBTI. There will not be a separate SCICAM workstation copy/backup.
     29
    2230**LBTO support**
    23 * IT support to install/set the workstations in the proper location, connect to the LBT network.
    24 * LBTO SW support may be needed.
    25 **Associated SHARK-NIR personnel**
     31- IT support to install/set the workstations in the proper location, connect to the LBT network.
     32- LBTO SW support may be needed.
    2633
    2734**Date performed and by whom**
    2835
    29 **Comments**
    30