Changes between Version 14 and Version 15 of docs/CommissioningPlan/P1.4
- Timestamp:
- 02/04/21 23:44:13 (4 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan/P1.4
v14 v15 6 6 • **Duration** : 1 day 7 7 **Description** 8 • At the LBT clean room, cable in the instrument. Power on the electronics, install workstations ,and connect SHARK-NIR to the LBT network.8 • At the LBT clean room, cable in the instrument. Power on the electronics, install workstations and connect SHARK-NIR to the LBT network. 9 9 **Prerequisites** 10 10 • All the necessary tools and safety features to do the cabling. A free and accessible network port to connect SHARK-NIR to the LBT network. … … 19 19 • SHARK-NIR can be accessed through the LBT network (e.g. Switching on/off services remotely from the control room). 20 20 **Notes** 21 21 * SCICAM is redundant with other SCICam computers inside of LBTI. There will not be a separate SCICAM workstation. 22 22 **LBTO support** 23 23 * IT support to install/set the workstations in the proper location, connect to the LBT network. … … 28 28 29 29 **Comments** 30 * for MM: check back up for SCICAM workstation. 30