Changes between Version 11 and Version 12 of docs/CommissioningPlan/P1.4


Ignore:
Timestamp:
02/03/21 11:37:42 (4 years ago)
Author:
kradhakrishnan
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • docs/CommissioningPlan/P1.4

    v11 v12  
    66•       **Duration**            :       half a day
    77**Description**
    8 •       At the LBT clean room, cable in the instrument. Power on the cabinets, install workstations and connect SHARK-NIR to the LBT network.
     8•       At the LBT clean room, cable in the instrument. Power on the cabinets, install workstations, and connect SHARK-NIR to the LBT network.
    99**Prerequisites**
    1010•       All the necessary tools and safety features to do the cabling. A free and accessible network port to connect SHARK-NIR to the LBT network.
    1111**Procedure**
    1212•       Carefully cable in SHARK-NIR.
    13 •       Switch on the electronics cabinets.
    14 •       Install the instrument workstation (and its copy/backup?) and the scientific camera (SCICAM) workstation in the server room.
     13•       Switch on the electronics.
     14•       Install the instrument workstation (and its copy/backup) and the scientific camera (SCICAM) workstation in the server room.
    1515•       Connect SHARK-NIR to the LBT network.
    1616*  Ready essential laptops ready with all the relevant software for the cleanroom activity. Check the connection with both the workstations mentioned earlier.
    1717**Success criteria**
    18 •       Electronics cabinets are powered on (working of led lights, fans, etc.).
     18•       Electronics is powered on (working of led lights, fans, etc.).
    1919•       SHARK-NIR can be accessed through the LBT network (e.g. Switching on/off services remotely from the control room).
    2020**Notes**
     
    2222**LBTO support**
    2323•       IT Support to connect to the LBT network.
    24        Any electronics support needed?
     24 SW support may be needed.
    2525**Associated SHARK-NIR personnel**
    2626