Changes between Version 11 and Version 12 of docs/CommissioningPlan/P1.4
- Timestamp:
- 02/03/21 11:37:42 (4 years ago)
Legend:
- Unmodified
- Added
- Removed
- Modified
-
docs/CommissioningPlan/P1.4
v11 v12 6 6 • **Duration** : half a day 7 7 **Description** 8 • At the LBT clean room, cable in the instrument. Power on the cabinets, install workstations and connect SHARK-NIR to the LBT network.8 • At the LBT clean room, cable in the instrument. Power on the cabinets, install workstations, and connect SHARK-NIR to the LBT network. 9 9 **Prerequisites** 10 10 • All the necessary tools and safety features to do the cabling. A free and accessible network port to connect SHARK-NIR to the LBT network. 11 11 **Procedure** 12 12 • Carefully cable in SHARK-NIR. 13 • Switch on the electronics cabinets.14 • Install the instrument workstation (and its copy/backup ?) and the scientific camera (SCICAM) workstation in the server room.13 • Switch on the electronics. 14 • Install the instrument workstation (and its copy/backup) and the scientific camera (SCICAM) workstation in the server room. 15 15 • Connect SHARK-NIR to the LBT network. 16 16 * Ready essential laptops ready with all the relevant software for the cleanroom activity. Check the connection with both the workstations mentioned earlier. 17 17 **Success criteria** 18 • Electronics cabinets arepowered on (working of led lights, fans, etc.).18 • Electronics is powered on (working of led lights, fans, etc.). 19 19 • SHARK-NIR can be accessed through the LBT network (e.g. Switching on/off services remotely from the control room). 20 20 **Notes** … … 22 22 **LBTO support** 23 23 • IT Support to connect to the LBT network. 24 • Any electronics support needed?24 • SW support may be needed. 25 25 **Associated SHARK-NIR personnel** 26 26