     1== P1.4 Cable in the instrument, power on, and connect to LBT network ==
     2•       **Phase**               :       1 
     3•       **Status**              :       Draft   
     4•       **Category**            :       Installation, integration, verification (C1)                           
     5•       **Recurrence**  :       once
     6•       **Duration**            :       2 hour(s)
     7**Description**
     8•       At the LBT clean room, cable in the instrument. Power on the cabinets, and connect SHARK-NIR to LBT network.
     9**Prerequisites**
     10•       All the necessary tools and safety features to do the cabling. A free and accessible network port to connect SHARK-NIR to LBT network.
     11**Procedure**
     12•       Carefully cable in SHARK-NIR.
     13•       Switch on the electronics cabinets.
     14•       Connect SHARK-NIR to the LBT network.
     15**Success criteria**
     16•       Electronics cabinets are powered on (working of led lights, fans, etc.).
     17•       SHARK-NIR can be accessed through LBT network (e.g. Switching on/off services remotely from the control room).
     18**Notes**
     19**LBTO support**
     20•       Support to connect to LBT network.
     21•       Any electronics support needed?
     22**Associated SHARK-NIR personnel**
     23•       JF, LM, MdP,
     24**Date performed and by whom**