| 1 | == P1.4 Cable in the instrument, power on, and connect to LBT network == |
| 2 | • **Phase** : 1 |
| 3 | • **Status** : Draft |
| 4 | • **Category** : Installation, integration, verification (C1) |
| 5 | • **Recurrence** : once |
| 6 | • **Duration** : 2 hour(s) |
| 7 | **Description** |
| 8 | • At the LBT clean room, cable in the instrument. Power on the cabinets, and connect SHARK-NIR to LBT network. |
| 9 | **Prerequisites** |
| 10 | • All the necessary tools and safety features to do the cabling. A free and accessible network port to connect SHARK-NIR to LBT network. |
| 11 | **Procedure** |
| 12 | • Carefully cable in SHARK-NIR. |
| 13 | • Switch on the electronics cabinets. |
| 14 | • Connect SHARK-NIR to the LBT network. |
| 15 | **Success criteria** |
| 16 | • Electronics cabinets are powered on (working of led lights, fans, etc.). |
| 17 | • SHARK-NIR can be accessed through LBT network (e.g. Switching on/off services remotely from the control room). |
| 18 | **Notes** |
| 19 | **LBTO support** |
| 20 | • Support to connect to LBT network. |
| 21 | • Any electronics support needed? |
| 22 | **Associated SHARK-NIR personnel** |
| 23 | • JF, LM, MdP, |
| 24 | **Date performed and by whom** |