== P1.3 Complete the installation of SHARK-NIR in the cleanroom with its electronics cabinet == • **Phase** : 1 • **Status** : Draft • **Category** : Unpack, Assemble, and Verification (C1) • **Recurrence** : once • **Duration** : 1.5 day **Description** • Install and integrate the different SHARK-NIR opto-mechanical components onto the mechanical structure. Install the electronics cabinets. Move the unit to the cleanroom. **Prerequisites** • All the necessary tools and safety features to do the installation, integration, and moving to the cleanroom. The mechanical structure to hold SHARK-NIR at the cleanroom should be assembled and ready to be used (with the possibility to move to the cleanroom). **Procedure** • Carefully integrate the cryostat unit with the derotator-optical bench unit. * Before installing the motor electronics rack in the cleanroom, take it to the LBT Platform cabinet (its final destination) shared with iLocater for sanity checks. • Set up the electronics racks. **Success criteria** • The SHARK-NIR is primarily assembled on to the mechanical structure. • Electronics racks are set up and ready to use. **Notes** **LBTO support** • Crane operator to lift and move stuff (mountain bay and/or cleanroom). • 1-2 crew to support installation procedure (mountain bay and/or cleanroom). * Access to the LBTO electronics cabinet where the motor rack of SHARK-NIR will be installed. * Optical bench and access to the clean tent. **Associated SHARK-NIR personnel** **Date performed and by whom** **Comments**